{"id":3753,"date":"2024-12-09T09:44:21","date_gmt":"2024-12-09T09:44:21","guid":{"rendered":"https:\/\/www.cervitech.nl\/?post_type=projecten&p=3753"},"modified":"2024-12-09T09:44:21","modified_gmt":"2024-12-09T09:44:21","slug":"berry-global-uk-2","status":"publish","type":"projecten","link":"https:\/\/www.cervitech.nl\/en\/projecten\/berry-global-uk-2\/","title":{"rendered":"RTO at Berry Global in Worcester"},"content":{"rendered":"

After a previous successful installation of an afterburner (RTO) at Berry Global in Hardenberg, CERVITECH BV and RELOX GMBH have now also successfully completed the project at the Berry factory in Worcester. The system is fully operational and approved by the customer. This project delivers significant benefits in energy efficiency and production performance.<\/p>\n\n\n\n

<\/p>\n\n\n\n

What did the project entail?<\/h5>\n\n\n\n

The RTO project at Berry Global in Worcester involved three main components:<\/p>\n\n\n\n

<\/p>\n\n\n\n

1. Projectmanagement<\/h5>\n\n\n\n

CERVITECH BV took on the complete project management, both from the Netherlands and on site in England. By working closely with Berry Global, we ensured that the project was delivered on time and met all the specifications and requirements.<\/p>\n\n\n\n

2. Energy efficiency improvement and connection of seven flex units<\/h5>\n\n\n\n

An important milestone was the successful coupling of seven flex units to the new afterburner. This adjustment resulted in:<\/p>\n\n\n\n